Lockheed Martin Adds $72.6M to F-35 Block 4 Development Contract

The US Navy has added $72.6 million in scope to a Lockheed Martin F-35 development contract to speed up Block 4 capabilities, according to a Department of War contract announcement reported on November 21, 2026. The money is for software and management support, not hardware.
Naval Air Systems Command at Patuxent River, Maryland, awarded the cost-plus-fixed-fee modification without competition. No funds were obligated at the time of award, and the work is expected to finish in March 2028.
Navy Adds $72.6M to Lockheed Martin’s F-35 Block 4 Contract
| Item | Detail |
|---|---|
| Customer | US Navy, Naval Air Systems Command (Patuxent River, Maryland), for the F-35 Joint Program Office |
| Contractor | Lockheed Martin |
| Value | $72.6 million added to the contract |
| Contract type | Cost-plus-fixed-fee modification |
| Competition | Awarded without competition |
| Scope | Program management, software engineering, “software engineering transformation” and cybersecurity support to accelerate Block 4 |
| Funds obligated | None at time of award |
| Work locations | Fort Worth, Texas (60%); Nashua, New Hampshire (16%); Baltimore (9%); smaller shares in Florida, California, New York and Arizona |
| Base contract | N00019-23-C-0009 (2023) |
| Completion | March 2028 |
| Reported | November 21, 2026 |
The modification raises the ceiling on an existing development deal rather than starting a new one. The Department of War announcement says the added work will “accelerate the development of F-35 Lightning II Block 4 capabilities.”
Most of the work stays where Lockheed builds the jet. Fort Worth accounts for 60% of it, Nashua for 16% and Baltimore for 9%.
What the New Money Pays For
The announcement lists four areas: program management, software engineering, what it calls “software engineering transformation,” and cybersecurity support. None of it is aircraft hardware.
That fits the shape of Block 4, which is a set of more than 80 classified and unclassified improvements that Lockheed is rolling out in stages across production lots. Much of it is software. It also depends on Technology Refresh 3, or TR-3, a $1.9 billion package of new computers, displays and memory that gives the jet the processing power Block 4 needs.
How Contract N00019-23-C-0009 Has Grown
The base deal, N00019-23-C-0009, dates to 2023 and covers continued development, test and integration of Block 4 upgrades, along with the training and combat data systems that go with them. It started as an undefinitized award with a not-to-exceed value of about $1.44 billion and has grown through dozens of changes since.
| Modification | Value | Focus |
|---|---|---|
| 2023 | $34.7 million | Program management, software engineering and cyber support tied to beyond-line-of-sight communications |
| January 2024 | Up to $97.4 million | Early integration of the AGM-88G AARGM-ER, plus reprogramming labs and mission data files |
| August 2024 | $611.3 million | Multi-ship infrared search and track and Band 5 radar warning receiver hardware |
| This award | $72.6 million | Program management, software engineering, “software engineering transformation” and cybersecurity |
TR-3 and the Block 4 Delays
TR-3 has been the main source of delay. It was due in April 2023, but hardware and software problems led the Pentagon to stop accepting new F-35s for about a year, until July 2024. Since then jets have been delivered with a truncated version of the package.
The Government Accountability Office said in a September 2025 report that Block 4 was at least $6 billion over budget and years behind schedule. It also said the effort would not be finished before 2031. The F-35 Joint Program Office has been splitting Block 4 and TR-3 into a separate major subprogram, a move Congress ordered in 2023. Until that work and a new cost estimate are done, GAO said, Block 4 will “have fewer capabilities, will experience schedule delays and will have unknown costs.”
| Measure | Earlier plan | Latest status |
|---|---|---|
| Block 4 capabilities | 66 by 2026 (original 2018 plan) | Date slipped to 2029; GAO says not finished before 2031 |
| TR-3 package | Due April 2023 | Deliveries paused about a year until July 2024; truncated version delivered since |
| Cost | Not restated here | At least $6 billion over budget (GAO, September 2025) |
| Waste heat (JPO) | About 30 kW in Block 3 | About 47 kW in Block 4 |
In February 2026, the Pentagon told GAO it planned to bring more digital twins, modelling and simulation into Block 4 development, and to add leading product development practices to the Block 4 acquisition plan by June 2026.
Other Block 4 Work on Separate Contracts
Other Block 4 work is moving on separate contracts. In April, Naval Air Systems Command ordered three new F-35 flight science aircraft, one per variant, for $177.5 million to support Block 4 testing. In September, Northrop Grumman received $124 million for parts for the APG-85 radar, the gallium nitride radar meant to replace the APG-81.
The Navy also finalised an order for power and cooling upgrades, needed because Block 4 adds heat. For background on another F-35 oversight issue, see our report on GAO’s findings on missing F-35 spare parts records.
Lockheed Martin Company Profile
| Item | Detail |
|---|---|
| Headquarters | Bethesda, Maryland |
| Founded | 1995 (merger of Lockheed and Martin Marietta) |
| Employees | About 121,000 (2024) |
| Revenue | About $71.0 billion (2024) |
| Segments | Aeronautics, Missiles and Fire Control, Rotary and Mission Systems, Space |
| Known programmes | F-35, F-16, F-22, C-130J, PAC-3 MSE, HIMARS, Black Hawk |
The new modification is small beside the programme it supports. It shows where the Navy is putting money to pull Block 4 forward: software and cyber work rather than new hardware. That reading is analysis, not a company or Navy statement.
F-35 Block 4 Contract FAQ
How much is the new F-35 Block 4 contract modification worth?
$72.6 million added to Lockheed Martin’s development contract, awarded by Naval Air Systems Command without competition.
What does the modification pay for?
Program management, software engineering, “software engineering transformation” and cybersecurity support to accelerate Block 4 development. It does not buy hardware.
When will the work be finished?
The announcement gives an expected completion date of March 2028.
What is F-35 Block 4?
The jet’s largest planned upgrade: more than 80 classified and unclassified improvements, much of it software, being added in stages across production lots.
Why is Block 4 delayed?
TR-3, the computer and memory package Block 4 depends on, slipped from April 2023 and paused deliveries until July 2024. GAO said in September 2025 that Block 4 was at least $6 billion over budget and would not finish before 2031.
- Department of War – contract announcement for the Lockheed Martin F-35 Block 4 modification (contract N00019-23-C-0009), as reported November 21, 2026
- Defence Blog – “Lockheed gets $72.6M to speed up delayed F-35 Block 4 upgrade” (November 21, 2026): defence-blog.com
- US Government Accountability Office – F-35 Block 4 report GAO-25-107632 (September 2025)
- Wikipedia – Lockheed Martin (company data)